Planning a construction project?
Whether you are building a new home, renovating an existing property, adding a structure or completing a plumbing project, you may need a building permit before work begins.
The Town of Osoyoos requires building permits to help ensure construction meets the BC Building Code, municipal bylaws and applicable health and safety requirements. Obtaining the necessary permits before starting work helps avoid delays, additional costs and potential enforcement action.
The Town's Planning and Development Services Department reviews building permit applications, issues permits and conducts inspections throughout the construction process.
Application Review and Permit Fees
Building permit applications are reviewed to ensure the proposed construction complies with the BC Building Code, the Town's Building Code Administration Bylaw, zoning regulations and other applicable requirements.
Initial plan review generally takes approximately three weeks for a single-family dwelling. Applications for commercial, industrial and multi-family developments may take longer, depending on their complexity.
Permit fees vary depending on the estimated construction value and type of project. Additional fees, plan review deposits and security deposits may apply as outlined in the Town's Building Code Administration Bylaw.
Accepted payment methods include cash, cheque, debit and credit card.
Construction must not begin until the required building permit has been issued. Starting construction without a valid permit may result in double the applicable permit fees, along with possible enforcement action.
View fees and charges here
Building Inspections
Once a building permit has been issued, inspections are required at various stages of construction to verify compliance with approved plans, applicable codes and safety requirements.
Depending on the project, inspections may include:
- Footings and foundation: After forms are completed and before concrete is poured.
- Foundation drainage: After perimeter drain installation and damp-proofing, but before backfilling.
- Underground plumbing: Before plumbing pipes and services are covered.
- Slab preparation: Before concrete is poured.
- Framing and sheathing: Once framing, bracing, fire stopping and associated work are complete.
- Insulation and vapour barrier: After installation and before work is concealed.
- Final inspection: When construction is substantially complete and before occupancy.
Other inspections may be required depending on the scope of work.
Additional Information to Consider
Zoning and Development Permits
A building permit does not replace zoning or development approvals. All construction must comply with the Town's zoning regulations, including permitted uses, setbacks, building height and density requirements.
Some properties are located within Development Permit Areas and may require an approved Development Permit before a building permit can be issued.
For zoning and development information, refer to the Town's Zoning Bylaw No. 1395.
Properties Near Watercourses
If your proposed project is within 30 metres of the high-water mark of a lake, swamp, pond or watercourse, or within 30 metres of the top of a ravine bank, additional requirements may apply.
A Riparian Areas Regulation Assessment and Watercourse Development Permit may be required before a building permit application can be accepted. Contact Planning and Development Services to determine whether these requirements apply to your property.
Home Warranty Insurance
New homes constructed in British Columbia by licensed residential builders are generally required to have third-party home warranty insurance under the Homeowner Protection Act and its regulations. Owner-builders may be exempt in certain circumstances.
For more information, visit BC Housing.